Recertification Deadlines, Notices, and Penalties.
P.E. #67462 · Level III CIT® #19397 · Engineering Business Registry #28738 · Miami · 41 Years Since Engineering Degree.
Florida law (F.S. 471.023) requires an Engineering Business Registry number to offer engineering services. Ours: #28738.
Updated November 26, 2026 · By Armando Longueira, P.E. #67462, Level III CIT® #19397.
★★★★★ 5.0 on Google · One engineering firm seals the complete recertification — structural, electrical, infrared, illumination, and guardrails.
Did you receive a Notice of Required Inspection? The report is due within 90 days of that notice. One engineering firm inspects and seals your complete package — structural, electrical, infrared, illumination, and guardrails. Sec. 8-11(f)(2)(E).
Call (786) 318-7203. Request a same-day estimate.
A complete package starts at $5,600.
"Armando Longueira, P.E. was a pleasure to work with. He was very professional in his approach and demonstrated a high level of expertise in the field of Electrical Infrared Thermography Inspection."
"Very professional, highly knowledgeable about the codes, extremely honest, and responsible with deadlines. Always available for any questions. I recommend him all the time."
Hablamos Español.
This page explains the notices, deadlines, extensions, repairs, and penalties of the recertification. The general rules are in our 40-year recertification guide.
How to read this page. Each rule is given in plain words, and the link after it opens the official text.
Deadline questions: 7 answers.
How Do You Check a Property?
Look the property up — by address or folio — on the County’s portal or with your city’s building department, before any notice arrives; the obligation runs with the structure’s age. Buyers should run the same check before closing.
In unincorporated Miami-Dade — a building whose folio number begins with 30 — check your status on the Recertification Portal, or call (786) 315-2373. Every other municipality keeps its own list — call them, or send us the address and we run the check.
A filed report is a public record, and anyone can request a copy. County recertification page.
What Notices Are Sent?
The Building Official sends two courtesy notices, two years and one year before the due year, and then the Notice of Required Inspection, which starts the 90 days. A courtesy notice that never arrives does not move the deadline. Sec. 8-11(f)(2)(D).
When Is the Report Due?
The report is due within 90 days of the notice, and you can file it early, from two years before the anniversary. Sec. 8-11(f)(2)(E).
The official may grant an extension of up to 60 days, on a written request from the professional of record with a sealed statement that the building can stay occupied. Sec. 8-11(f)(2)(I).
What If Repairs Are Needed?
You have 150 days from the notice to finish the repairs that need no permit and to obtain the permits for the rest; permitted repairs then follow the timeline of the permit. Sec. 8-11(f)(2)(F).
- During the repairs, the professional of record gives the official a letter stating whether the building can stay occupied — often called a Safe to Occupy letter; each letter is valid for up to 180 days. Sec. 8-11(f)(2)(G).
- When the repairs are done, the same professionals file an amended report, often called the final report. Sec. 8-11(f)(2)(H).
- Do not start repairs without permits: most repairs need one, and work without a permit can become a violation. County guidelines, 2025.
- The County may ask the owner to shore up the structure while the repair plans are prepared. County page.
What If You Miss the Deadline?
Miss the 90-day deadline and the County issues a citation without further notice. There is an initial penalty, further penalties can add up for each violation, unpaid amounts can become a lien, and a late report pays a late fee. The official may also order the electricity disconnected, and an unsafe building can be ordered vacated. County page.
- Electricity. The official may order the electricity disconnected. First, a notice goes to the owner by certified mail and stays posted on the building for at least 5 business days. Sec. 8-11(f)(2)(J).
- Tenants. The association, manager, or landlord must pass that notice in writing to all unit owners and tenants within 24 hours, and send proof to the Building Official within three business days. Sec. 8-11(f)(2)(J).
- How to stop it. A sealed statement from the professional of record that the building can stay occupied stops the disconnection. Sec. 8-11(f)(2)(J).
- Unsafe structure. A building that stays out of compliance may go before the Unsafe Structures Board and be ordered repaired or demolished, and where there is immediate danger the official may order the occupants to vacate. Buyers, lenders, and insurers often ask for the recertification status, so an open case can also slow a sale, a refinance, or an insurance renewal. Sec. 8-5.
To stay in compliance, start the inspections when the first courtesy notice arrives.
Is your deadline close? Send us the notice and the property address. We answer the same day with the scope and the price.
We Never Got a Notice. Are We Exempt?
No. Miami-Dade’s two recertification notices are a help, not a condition. If the Building Official does not send them, Miami-Dade still requires the owner to recertify on time. Sec. 8-11(f)(2)(D).
Our Building Was Never Recertified. Are We Late?
For a building built in 1982 or earlier, the first recertification is due at 40 years and then every 10 years. If that date has passed and no report is on file, the building is already late. Sec. 8-11(f)(2)(A)(ii). File as soon as you can: a late owner can get a civil violation notice and a referral to the Unsafe Structures Board. Sec. 8-11(f)(2)(J). Newer buildings follow the dates in When Is My Building Due?
Ready to Schedule?
To schedule your recertification, or to ask about its price, you can email us, call us, or fill out our contact form. A pre-estimate is also available online.
Related: Thermography · Electrical · Structural · Parking-Lot Illumination · Milestone · Español.